on 04-30-2015 1:43 PM
A product is sourced by store S001 from Regional DC R001. In product master for S001 I specified procurement type as F and PDT = 14 days. Also maintained the transportation lane. When I run either SNP or PPDS Heuristics, in either case the PDT is not considered during the run.
By that I mean if a preq is required on May 20th in S001 the Preq Rel date in R001 should appear as May 14th. However the PDT is being ignored and the dates appear exactly the same in both locations.
Am I missing a master data or a parameter?
in S001 you created a PR P001, then in R001, if you say about R001 it is PR rel, for sure, the req date of P001 is the same required date in S001------------PDT and trans horizion and MOT duration will be considered to create recipe in R001 location, like PR or planned order in R001. but not display the demand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.