on 04-29-2015 8:42 PM
Dear Gurus,
would you please let me know if standard SAP would not allow blocked line items to be rescheduled? I have an issue where blocked sales orders "Delivery Block" are not getting rescheduled when running V_V2. Thanks for youe help!
Yes it is a standard SAP functionality. If there is a Credit block or Delivery block in sale order, system will not reschedule such of those orders.
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Lakshmi! we had a custom code to put orders on a soft delivery block if we cannot fulfill the whole order. here is me scenario:
Line item 10 we have inventory
Line Item 20 we do not have inventory
the order is on a soft delivery block "order cannot fulfill"
Production put in a production order to make inventory available, once the production order is complete and inventory is available we would like the reschedule job to pull this order to the pool of orders it is checking. is there a way to be able to do this? Thanks again for your help!
Hi,
Do you have the fixed date and quantity field ticked on. If this is ticked on, it will not reschedule.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.