Order status mismatch at SAP R3 & APO.

Hello,


We have some order with different status at R3 & APO, When we pushed orders form R3 to APO via CCR, getting below errors at CIF logs:

"Order could not be scheduled"

"An activity could not be scheduled/rescheduled"


We have MTO scenario, business create sales order at R3, after heuristic run, plan order created for sales order, business convert plan order to process order manually at APO.

We are using PDS for master data.

Kindly help us to resolve this.

Thanks,

Nilesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Apr 29, 2015 at 12:53 PM

    Hi Nilesh,

    Where are MTO pl.orders created in R3 or APO?

    If is in R3 and you just convert them in APO you need to be sure that all operations and activities maintained in R3 are transferred in APO at PDS PPDS level!

    Thanks, Marius


    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 29, 2015 at 03:59 PM

    Hi

    Can you check whether there was Process Order created for the same ProdLoc combination Earlier and sent to ECC but later deleted in APO (May be by Heuristics settings / Manually / RLCDEL) before the CIF happened.

    Thanks

    Vinoth