Hello All,

I have manually entered forecast for 01st of June 2015 but the same forecast is showing in previous bucket of planning book.

In this case system is showing required/available data as 05/31/2015 at 20:00:00 hours.

Please take a look at below screen snaps & help me in understanding which setting is causing this behaviour.

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

It could be a issue due to different timezones maintained across the.

Check.

User Timezone. SU01D

Version Timezone. /SAPAPO/MVM

Location Timezone. /SAPAPO/LOC3.

Thanks

Vinoth

Answers (3)

Answers (3)

Former Member
0 Kudos

to exclude the possible root cause, try to put a forecast on May 30 or June 1st, see if this is impact by calendar setup, like none working day? or, period factor?

thanks

former_member187488
Active Contributor
0 Kudos

Hi,

You can check your production calendar of the location.

BR, Ada

former_member182449
Participant
0 Kudos

Hi Shaiz

I need you to check in the strategy planning which which you are using the scheduling type

I need you to try backward + Reverse

Regards

Rami

former_member406212
Participant
0 Kudos

Thanks Rami.

former_member182449
Participant
0 Kudos