Former Member
Apr 21, 2015 at 05:07 AM

Query on retaining old BOM for a Network

13 Views

Hi Gurus,

We have a scenario where a network start date is 01.12.2014.

For the network, a BOM is assigned for which we have deleted the component ABC and have added a component XYZ.

The validity start date of the changes done to the BOM is 01.04.2015.

We wanted the component ABC to be retained for the network and the component XYZ should not be added to the network (since the validity start date of the network is 01.12.2014 and the validity start date of the changes done to the BOM is 01.04.2015).

However, we have observed that the component ABC is deleted from the network material component list and the component XYZ is added to the network even when the validity start date of the changes done for the BOM is far later than the validity start date of the Network.

Kindly request your help on letting us know how to retain the old BOM for the network and not the modified BOM.

Thanks and Regards,

Sanju