Hi all,

We are mapping a business process where an SO is created for an internal customer, and material is procured from vendor.

When they do GR for the PO they want to consume the goods and statistical goods issue is performed against the SO/delivery.

When it comes to procuring an Asset, we are not able to create a schedule line category with account assignment category A - asset.

We are getting the error "V1768 - Unpermitted values for KZVBR A or SOBKZ for acc. assignment cat."

can anyone please suggest what is going wrong here ?

I understand the error message is saying that - Consumption indicator KZVBR in the account assignment category A is not permitted. It has to be space, V, E etc but not A.

But then how to map this scenario in case of Asset procurement ?

Thanks,

Sudheer.

Message was edited by: Sudheer K