Dear all,

Please look into the issue i am facing. I have created a material with planning strategy 50. Run MRP against sales order. After confirming production order, i have opened cost analysis.

Sales Order:

Cost Analysis:

Material Standard Price:

As per cost analysis, Final goods receipt price is coming from plan cost of component materials and activity price of confirmations. As you can see, Standard price of material is completely different which is not reflected in costing. How is this cost coming? What is the configuration? If i want only standard price to be fetched, what configuration to be done?

If i use any other strategy, or no strategy, final goods receipt price is coming from Standard Price of material.

Thanks,

Sayak

Attachments

cost1.JPG (127.5 kB)
cost2.JPG (75.8 kB)
cost3.JPG (107.2 kB)