Dear All,

The Activity rate Maintained in KP26 is 10 . But when we do the confirmation IW41 , the rates are doubled. ( No Exits in place)

Your help will be much appreciated.

Regards,

Shareeq

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Mar 31, 2015 at 01:28 PM

    Thanks everyone. We located the problem. The rate was not maintained properly monthwise.

    Thanks for your time,

    Regards,

    Shareeq

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 31, 2015 at 08:37 AM


    Hello Shareeq,

    check the capacity header of the work cente used for time confirmation and the no of individual capacities entered (..maybe it's 2).

    Regards,

    P.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 31, 2015 at 08:14 AM

    Hello

    Could you please share screen shot of KP26

    Br

    Rakesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.