on 03-26-2015 6:34 AM
HI ALL
I want to settle no material production order to a G/L account which is also a cost element , so I need to assign a cost center to it. Of course I can enter a cost center in settlement rule manually . However this may cause a mistake, cause the cost center will be different according to different plant or profit center. So I am wondering if there is any way to set cost center a default value according to plant or profit center.
I've tried COOM0003 PPCO0001 and other user exits ,
I also tried to do enhancement in INCLUDE LCK02FAZ / FORM generate_hdr_settlement,none of them works.
Thanks a lot.
Danielle
Hello Lian,
As per standard SAP system design it is not possible to create automatic settlement rule receiver if a production order is created without material you must enter it manually
CO07 rework orders are created without material.
Please go through OSS note 1929029 - FAQ: Settlement rules in production order
Refer question 2:
Question:
When settlement rules can be created automatically?
Answer:
The system only determines the following settlement receivers automatically for production orders. Settlement rules with other settlement receivers cannot be created automatically.
- Material
- Sales order item
- WBS element
- Higher-level order (in collective order).
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.