Hi, I have question that I can get a good answer for a while now. I just wanted to know if this even possible.

I created a new Work Center using CR01. (lets say 9999)

Now all I need to do is to add (not replace) this work center 9999 to multiple routings for different part numbers. (1000 part numbers).

Can this be done with mass add somehow, instead of me going into CA02 of each part number and doing this manually.

Thank you in advance,

Leo

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Mar 24, 2015 at 04:04 PM

    Hi Leo


    You can do that using transaction CEWB. You will find several threads about this transaction.

    BR
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.