Hi Experts,

I Just want to know how assign the cost centre's to positions in a batch. Is this Possible through LSMW. if yes,then kindly let me know the steps to be followed to do it.

Kindly help me in this as i am a fresher no getting idea how to handle this in a batch.

Regards,

Jyotesh.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Mar 23, 2015 at 06:19 PM

    You should be able to accomplish via BDC. Set up recording via SHDB and then execute via SM35.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 24, 2015 at 12:39 AM

    Steps 1-3 in dev config client. Step 4-5 in Dev test client.

    1. In SHDB txn, create batch recording for transaction PO13. Do not use selection of object id or period, etc. Enter these values. Selection muddles up the recording as I have experienced many times.

    2. In txn LSMW, create an object, use the batch recording created in step 1, go through all the steps under this before you create a batch session,

    3. Create/update transport/s for the above items in steps 1 & 2.

    4. In txn SCC01, or 07, copy the transport to dev test client.

    5. Create some data in an Excel and save as *.txt file.

    Execute LSMW bdc session creation.

    Execute bdc session in foreground with the option to show errors only. Keep the data.

    In PO13 txn, display the data created and check it is ok. Else repeat from step 1-3, modifying any part as required.

    6. Move the transports to Test system/client and repeat step 5 in this client.

    You may get UAT also done by user, unless you run the data load in production client with a generic support user id (not a personal id), as some organizations do with user approval

    7. Then move the transports to prod

    Run the LSMW with actual data and bdc session execution, starting with one or two records; ensure it is ok; then you can run for all data or in batches.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2015 at 05:03 AM

    This is possible with LSMW go to transaction PP02 and enter necessary details on the screen Plan version, object type,object id,info type, sub type, planning status validity periods then click on create maintain related object details and save the record this entire process for recording for the same create LSMW and upload the data before this test it properly accordingly it works.

    Regards

    Venkatesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.