Planned orders appears in RRP3 but when published doesn't appear in ECC ?
Help me with CIF procedures to bring it to ECC. (without using C5) because i need to convert to production order.?
Thanks
Ohio
Hello Rahul,
Please check the publication setting for location in-house production in /SAPAPO/CP1.
Check active integration model in CMF5, if missing create the integration model by CFM1 and CFM2.
Also you can run the delta report /SAPAPO/CCR or post processing report /SAPAPO/CPP1 for planned order to transfer.
Also check the CIF application log SLG1.
Best Regards,
R.Brahmankar