on 03-18-2015 10:03 AM
Hi Experts,
We are facing an issue where we see that for a particular resource, capacity is avaliable in resource master till end of the horizon but when we check the resource chart in detailed scheduling board there is no capacity shown there. The resource chart simply shows downtime.
Appreciate your inputs on this issue.
Regards,
Shweta
Hi,
Could you run a consistency check on resource (om17)
Also please check this report. /SAPAPO/CRES_CREATE_LC_RES
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Shweta,
Do you have problem with only one resource?
Is this resource having the Bucket oriented or Time-continuous capacity?
Also check resource is available inactive model 000.
Check the calender assign to resource are having correct working days.
Check Active Available Capacity Variant assign to resoucre
Or try to re-CIFf the recourse from ECC and check the DS board again.
Best Regards,
R.Brahmankar
Hi,
I think that your option for APO work center capacity is from external capacity (ECC system). Check this in the work center, tab External Capacity. If the check box External Capacity is selected this means that you use the capacity of the work center from the ECC system. This is the reason for why you have capacity in the work center (APO system).
For downtime check the tab Downtime at work center level. Normally you will find Downtime defined for a period (with start & end date). This is the reason for why you see in the DS board just downtime period and no capacity for a certain period.
You can also check the calendar resource on APO side!
I hope this can help you!
Thanks.
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.