Lot size to consider fure sales orders to create one planned order

former_member232086
Participant
0 Kudos

Team,

Which lot size should I consider to consider the future sales orders and system should create only one planed order

Scenario below

I have sales order for current month 50 and for april 2015 100

Lot size in Material master is monthly lot size (   MB) when I run MRP system create two planned order ..one for current month and one for April

Now I need to create only one planned order here ..clubbing the current month and april sales orders..

Which lot size should I use here?

Thanks to confirm

Vijesh

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Vijesh,

You can use the period lot size like MB, you can create new one by coping MB to ZB in OMI4 here define No. of periods = 2  in lot size so it will consider the requirements of two months.

Best Regards,

R.Brahmankar

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You can define lot sizing procedure, which will follow the periods defined on your planning calendar.

Then, on your planning calendar, you define the desired perido, which can be, for example, the entire year.

See document for an example.

Regards

Caetano

Former Member
0 Kudos

HI Vijesh,

may be you have considered this.

But, lot for lot with planning horizon (of say 45 days) will not solve your problem??

i Guess you want time based lot size planning but, should consider left over from previous time periods also?

is that what you are looking for?