on 03-14-2015 12:40 PM
Dear Expert,
Kindly Advise how to use Planning heuristic SAP_Multi_SCH During the Planning Run , what's the sequence of Steps should I have ?
Regards
Rami
Hello Rami,
Have you activated the business function SCM_APO_PPDS_PI?
You can execute /SAPAPO/CDPS0 Detailed Scheduling Planning Board for Heuristic SAP_MULT_SCH
Please refer SAP help document,
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rami,
Run transaction /SAPAPO/CDPS0 for the Detailed Scheduling Planning Board.
Select the overall profile SAP001 and planning version 000.
Enter the resource, location, or product in which the orders exist. Choose Execute.
Choose Profiles and select the heuristic profile defined in Customizing. Then choose Copy (Enter) to save the setting.
Select a resource with the orders.
Choose --> Functions--> Heuristic --> Multi-Resource Scheduling Heuristic to run the heuristic.The orders are scheduled in alternative modes, and different sources of supply are chosen after the switch over time.
Best Regards,
R.Brahmankar
Hello,
You can execute this Heuristic from/SAPAPO/CDPS0 - Detailed Scheduling Planning Board - Variable View not from /SAPAPO/CDPSB0 - Production Planning Run as per the heuristic profile which should have the heuristic SAP_MULTI_SCH as it is scheduling heuristic not planning.
In /SAPAPO/CDPSB0 - planning run you can use SAP_REM_001 Multiresource Planning (Equal).
Best Regards,
R.Brahmankar
Hello Rami,
I dont know if you can use this SFW heuristic in /SAPAPO/CDPSB0 - Production Planning Run .
For more information, see the system documentation for the heuristics. To call up the system documentation for a heuristic, in Customizing for Production Planning and Detailed Scheduling (PP/DS), under Maintain Heuristics, select Information for the heuristic.
Please refer SAP help for more details,
http://help.sap.com/saphelp_scm50/helpdata/en/2e/c0703713bf277ee10000009b38f8cf/content.htm
Regards,
R.Brahmankar
Hi Rami,
Kindly follow the following steps in order to execute the heuristics 'SAP_Multi_SCH' using production planning run i.e., using transaction /SAPAPO/CDPSB0
1. You need to have the customizing settings done for the heuristics, this is done in/SAPAPO/CDPSC11
2. Go to transaction /SAPAPO/CDPSB0, enter planning version , time profile and propagation range(you can use SAP provided default time profile and propagation range)
3.Under the tab step 1, select you 'SAP_Multi_SCH' heuristics
4. Under planning objects select 'Products
5. Enter the product and location details in the screen below.
6. Click on execute.
Note: You can as well check the check box for Display logs in order to check the logs.
The heuristics gets executed.
Hope I have answered your question.
Regards,
Jyoti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rami,
Kindly follow the following steps in order to execute the heuristics 'SAP_Multi_SCH' using production planning run i.e., using transaction /SAPAPO/CDPSB0
1. You need to have the customizing settings done for the heuristics, this is done in /SAPAPO/CDPSC11
2. Go to transaction /SAPAPO/CDPSB0, enter planning version , time profile and propagation range(you can use SAP provided default time profile and propagation range)
3.Under the tab step 1, select you 'SAP_Multi_SCH' heuristics
4. Under planning objects select 'Products
5. Enter the product and location details in the screen below.
6. Click on execute.
Note: You can as well check the check box for Display logs in order to check the logs.
The heuristics gets executed.
Hope I have answered your question.
Regards,
Jyoti
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
I can't use Finite Requirements Planning , experience has shown that this method can generally lead to serious disadvantages with large data volumes, both in terms of the performance and the quality of the solution. Consequently, SAP has been officially advising against using this “finite MRP run” since Release 4.0 of SAP SCM and now only allows this procedure to be used following consultation with SAP or in very special scenarios
How you use it This heuristic in Planning Run ?
Regards
Rami
Hi Rami,
Where to use heuristics in the sequence on what you want to achive looking at current sequence
Is only purpose for using this heurisitcs is becuase you are using alternative PDS and want to shift some order to alternative PDS to achive capacity leveling then you can run it just beofre optimization step and try.
You should test it out first. But I will like to listen from you exact business requirement then it would be easy to guide about steps.
Regards,
Santosh