Inventory in ECC is not updating against STO, after Goods issue in EWM

Hi Experts,

Pls throw some light and give me inputs in solving my issue.

My Scenario is STO (Plant to Plant within comp.code) integrated with EWM:

1. Created STO: (Supplying plant/sloc and Receiving plant/sloc are EWM managed)

2. Created Outbound delivery: Distributed successfully to EWM

3. Done the all activities in EWM like Picking, Loading & Goods issue

4. In ECC stock is not reduced and no update of Mat.doc/indbound, and still the ECC Outbound delivery is in open status

5.If I want to try post MIGO wrt Outbound or STO PO is also not possible as my Outbound delivery is greyed out (once its distributed, its not allowing to change).

Thats how I got struck. Dont know what to do, If I am right I followed the correct process.

Thanks to All

Srinivas

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Mar 14, 2015 at 10:23 AM

    Hi Srinivas,

    This gives me an idea that you delivery document may be stuck in either inbound queue of ECC(smq2) or outbound queue of EWM(smq1).

    In both the queues search first with the delivery number in the stuck queue entries. Once found, check why queue was stuck and then reprocess the queue.

    Regards,

    -Harsha

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 17, 2015 at 06:48 AM

    Hi Sreenivasa,

    1. The issue with updation of stock back to ECC could be because of some missing links/ config. You will have to check this in SMQ1/ SMq2/ SLg1 as suggested by Shriharsha. You can post a screenshot of the log in case you need more help on this.

    2. You can setup automatic creation of inbound delivery for replenishment deliveries. System creates an inbound delivery in the receiving plant with respect to the outbound delivery based on output determination procedure. To enable this, maintain output type SPED in the output determination procedure assigned to delivery type NL.

    LE --Shipping -- Basic shipping functions --Output Control --Output Determination --Maintain Output Determination for Outbound Deliveries

    Based on the above setup, system will automatically create an inbound delivery in receiving plant when you post GI in the supplying plant. You can then complete putaway activities in the EWM receiving plant wrt this inbound delivery.

    Regards,

    Smitha

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi ,

      I am also facing the same to inbound delivery creation .

      Are you able to get to the end of the issue so far, please let me know any additional config

      you have done apart from the setting above .

      Refer to the below screen shot for more info .

      Not sure what is the next step as I have done all the necessary config .

      Please help

      Thanks

      Richard

      pastedImage_0.png (73.6 kB)

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.