on 03-13-2015 6:50 AM
We have some Z report development using Report painter for the project , we call it is project control sheet, it contains many fields along with the commitment values for the WBS.
Z report values differs from the cji5 values..when we drill down to the Z report it actually takes you to the different value.
we had reconstructed the project info record using CJEN. but no use .
CJI5 values are correct but custom report has the issue.
Can you please help
Hi sunil,
Thanks for the reply.
The issue is not with the commitment value in CJI5 , but on the custom report the value is 67746 and if i drill-down on the same value , it shows me 3176 ...(CJI5 value and the value i get after drilling down is same now i.e. 3176)
(the incorrect values are coing for a particular project only, for rest of the projects report painter is working fine )
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
Thanks for the help.
Further addition to the problem.
The commitment values are different in below 3 reports :
S_ALR_87013542, S_ALR_87013558 and CJI5
What could be the reason. have implemented the Note :0001746429
1. Please run report RKANBU01 for the incorrect projects in question, this will update any incorrect commitments. Further details can be found
in note 152571.
2. After running the reports above, please run report RKACOR04 as this will correct any problems between the line item tables and the total
record tables.
3. After running the above reports, please run transaction code CJEN for all the projects as this is very important so that the database gets
updated.
4. Finally run report CJBN which rebuilds the availability control for each project.
But of no use .
Hi Mandar,
Please check below settings for commitment values.
Name | From | text | to | text |
Version | 0 | Plan/Act - Version | ||
Value Type | 21 | Commitments from Purchase Requisition | ||
Value Type | 22 | Purchase Order Commitment | ||
Value Type | 23 | Reservation Commitment | ||
Value Type | 24 | Funds Commitment | ||
Value Type | 26 | Commitments from Transfer Price Agreemen | ||
Object ind. | P | Project item | ||
Object ind. | 1 | Order plan values: appended, apportioned | 9 | Order values: not appended, deleted |
Debit type | 1 | Costs and credit-side payments |
|
these values need to set in form or you can use form 12KST1A Costs: Budg/Act/Cmmt
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.