PPM 6.1 - Capacity planning - upload planned demand from project to Item and Bucket level

Hi

I'm struggling a bit to upload capacity demand from the project to Capacity planning on Item and Bucket level. I get no values in the Assigned Resources Category on Item level. I've ran report /RPM/FICO_INT_PLANNING, but no values are displayed.

I'm pretty sure I've missed some basic customizing, but cannot figure out what is missing. Configuration related to Rollup should be correct.

Any ideas?

Thanks,

Lars

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 12, 2015 at 11:22 AM

    Dear Lars,

    have you maintained "Define Capacity Planning Settings" in the customizing path:
    "Portfolio Management > Base System Interfaces > Capacity Planning Settings"?

    Best regards,
    Judith

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Judith,

      thanks a lot, that solved my problem. In the "Map capacity view to role functions" I had missed the Amount setting. I updated this to Resource Assignment and then everyhting worked as planned :-)

      Br,