on 03-11-2015 5:50 AM
Hi all
I have a maintenance plan which have the time of call object as 3 months.After three years i want to change the duration i.e package as 9 months.I added the package in maintenance strategy and added that to task list.After scheduling i can see that a next call is after 3 months. But i want it to be 6 months. please suggest what is missing.
Thanks
Kartik
Greetings Kartik,
Please restart the Plan from a date 3 months ago. Please test this in IP10 and confirm. Consider any other packages apart from 3M and 9M.
EDIT: Sorry, I misread your question in the initial answer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.