Maintenance plan change

Former Member
0 Kudos

Hi all

I have a maintenance plan which have the time of call object as 3 months.After three years i want to change the duration i.e package as 9 months.I added the package in maintenance strategy and added that to task list.After scheduling i can see that a next call is after 3 months. But i want it to be 6 months. please suggest what is missing.

Thanks

Kartik

Accepted Solutions (1)

Accepted Solutions (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Kartik,

Please restart the Plan from a date 3 months ago. Please test this in IP10 and confirm. Consider any other packages apart from 3M and 9M.

EDIT: Sorry, I misread your question in the initial answer.

Former Member
0 Kudos

Thanks Sebastian Lenartowicz, its solved