Skip to Content
0
Mar 09, 2015 at 06:04 PM

PS Activity Planned costs not updated with KP26 Changes

477 Views

Hi,

We have maintained activity rates in KP26 and when we plan activity the system is using the planned rates from KP26 - this works as expected however if I change the rate in KP26 for example from £50 to £70 and go back the activity in CJ20n and run the edit-costs-calculate and also edit-costs-update then run edit-costs - actual/plan the planned value of £50 is still being used. I would expect the system to use the £70 rate.

I have checked in OPUV and the setting "Determine planned costs" is set.

In OPL1 I have the following settings:

has anyone come across this issue before?

thanks

Joe

Attachments