Heuristic SAP_PP_009 (Bottom Up) & Finite scheduling

675 Views

I want to execute heuristic SAP_PP_009 and execute also finite scheduling. Standard SAP does not allow it. Using note 560969 it is possible to use a finite strategy in SAP_PP_009 although it still does not recommend it. I implemented it and I used other finite strategies like Find Slot.


Finite scheduling indeed worked but production levels did not work correctly. I had many cases where production orders of next level started before production order of previous level finished.

What would you suggest me to do?

I mean which other heuristics I should use in order to achieve finite scheduling after executing Bottom Up without damaging production levels?

thank you