on 03-04-2015 12:26 PM
Dear SAP experts,
In our concern, we have a requirement with the below requirement.
Lead time for material.
Example
Supplier Country | Supplier agreed departure date | Shipping/Sailing time | Custom Clearance | Total Lead Time |
European | 15 days | 15 days | 10 Days | 45 Days |
GCC | 15 days | 5 days | 10 Days | 30 Days |
Local - KSA | 15 days | 5 days | No required | 20 Days |
We need best solution for the above requirement.
Ravi
Hi,
Create separate purchasing group for European, GCC & Local – KSA and then maintain the delivery time with following options and chose best one option.
Option-1: Maintain the delivery time in OMDT for plant with purchasing group for European, GCC & Local – KSA
Option-2: Maintain the delivery time for material with plant, purchasing with purchasing group for European, GCC & Local – KSA.
Option-3: Maintained a custom table where keep your all different segments of delivery date and total delivery time pick to purchasing document creation.
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
are you using scheduling agreement ?
if yes , what ever the delivery date mentioned in ME38 .GR will be done on that particular date
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Anil,
kindly provide your reply for this below requirement.
Example:
Supplier Country | Supplier agreed departure date | Shipping/Sailing time | Custom Clearance | Total Lead Time |
European | 15 days | 15 days | 10 Days | 45 Days |
GCC | 15 days | 5 days | 10 Days | 30 Days |
Local - KSA | 15 days | 5 days | No required | 20 Days |
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.