Purchase requisition delivery date before the requested/created date

100 Views


Dear Experts,

We are getting an issue that Purchase requisitions created by APO are having Delivery Date one day before of requesed Date.

Eg Purchase requistion created on 20.02.2015 and having delievery date on 19.02.2015.

I have checked contract, Purchase info record Tlane all master data settings are ok.

Planned Delievery Time maintained in the info record is 0 and GRPT time is 1 day.

Same vendor, contract, PIR exists for 2 material, But we are facing issue only for one material.

It is an urgent issue , if anyone is having any idea , suggestions please reply to me if any information required will update here.