on 03-02-2015 10:06 AM
Hi All,
I am bit confused regarding demand transfer form my Capacity Planning to cProjects roles.
Just wanted to know if it is possible to transfer demand many time for different Period to cprojects Roles? if yes then How, I am trying to transfer demand for already transfered role but when I am trying to do it other time for same role it Grayed out...
We are using PPM5.0
Thanks
Amit
Dear Amit,
the demand of capacity planning can be transferred to roles in Project Management only once. You
can find the check in webdynpro /RPM/FIN_CAP_PLANNING, view VI_TRANSFER, method
CAP_GET_TRANSFER_MAP.
Best regards,
Judith