Demand Transfer In SAP PPM

Hi All,

I am bit confused regarding demand transfer form my Capacity Planning to cProjects roles.

Just wanted to know if it is possible to transfer demand many time for different Period to cprojects Roles? if yes then How, I am trying to transfer demand for already transfered role but when I am trying to do it other time for same role it Grayed out...

We are using PPM5.0

Thanks

Amit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 05, 2015 at 10:32 AM

    Dear Amit,

    the demand of capacity planning can be transferred to roles in Project Management only once. You

    can find the check in webdynpro /RPM/FIN_CAP_PLANNING, view VI_TRANSFER, method

    CAP_GET_TRANSFER_MAP.

    Best regards,
    Judith