MRP NEUPL

Hi,

Despite the daily MRP job runs with NEUPL parameter, it doesn't select all the materials and we have some materials that hasn't been planned for one day.

¿Any idea of what could be happen?

Thanks.

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Mar 01, 2015 at 11:09 PM

    First of all. ¿Is it possible that a material can be deleted automatically from the MRP list due for any reason?

    I'm not sure if these material have never been in the MRP list or, for any reason, have been deleted of it.

    Thanks

    Regards.


    MRP1.jpg (84.2 kB)
    MRP2.jpg (88.3 kB)
    MRP3.jpg (89.2 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 01, 2015 at 08:39 AM

    Hi,

    There could be multiple reasons for the same. The materials you are referring are never planned before? If so, please check the MRP type in material master. If that is not PD or VB, then (say something like ND) it will not be planned.

    another reason could be your selection in MRP run.

    Please specify more details

    Thanks

    Prem

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 01, 2015 at 12:35 PM

    Hi Óscar,

    Note that NEUPL runs the MRP only if the material has an entry in the any planning file entry (MD21).

    NEUPL does not create any planning file entry. Check this note:

    206666
    - MRP: Control parameters during planning

    With MDAB you can generate entries in the planning file entry in background.

    Kind Regards,

    Mariano

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 01, 2015 at 04:46 PM

    Oscar,

    As stated above please show us the MRP views for that particular materials?

    Also show MD04 snap shot and Please check any Planning file entries exists for those materials for NEUPL in MD21 as Regenerative planning (NEUPL): System plans all the materials that are contained in the planning file.

    If not create a planning file entries MD20 or in background in MDAB and re run MRP.

    BR
    KK

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.