Report for Task list with assigned Materials which were already deleted

Jan 30, 2017 at 06:21 AM

51

avatar image

Hi

Anyone had come across a report that can enlist task list with materials and determine if the materials were already deleted from the system/plant etc.?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Peter Atkin Jan 30, 2017 at 11:22 AM
0

Not that I know of.

We are writing our own Inconsistency Report which, amongst other things, checks in Task Lists, BOMs, Orders for material which have a deletion flag set at System/Plant level.

You could probably write a simple SQVI/SQ01/2 report for this data.

PeteA

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi Pete,

Thanks, i was wondering if you have had created or used a user exit upon saving that will tell that the material has been deleted on the task list?

0

Have a look at BADI EAMCC_DOCUMENT_BADI_GUI via SE18

PeteA