Delivery date of PR in past

Former Member
0 Kudos

Hello,

We are having one PR which is created by MRP run. PR is created with the delivery date in the past.

PR requested date   :20.02.2014.

PR release date       :19.02.2014

PR delivery date       :19.02.2014.

Planned delivery time : 1.

GR processing time    : 1.

We are using APO  for planning.when i tried to create a PR manually for the same material, below dates are got picked.

PR requested date : 26.2.2014

PR release date     :26.02.2014

PR delivery date     : 27.02.2014

Can anyone explain this?

Thanks,
Sankar.


Accepted Solutions (0)

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Sankar,

PReq delivery date of the purchase requisition consider the WEBAZ. Fisrt check you have same GR posiing time in ECC and APO.During this process, the factory calendar is taken into account.Variances occur if WEBAZ and the calendar do not match in the both systems.


Also check when this PR was created by MRP. In your both the case PR requested date is different  20.02.2014 and 26.2.2014.


What is result when you create manaul PR in ECC?


Go to SPRO > Materials Management > Purchasing > Environment Data > Define Attributes of System Messages > System Messages - Here make message no. ME039 i.e. Delivery date is in the past as E= Error.


Best Regards,

R.Brahmankar

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please observe that you cannot compare the MRP logic with the manual creation of a PR, since both are very different.

On the customizing transaction OPPQ, the flag "start in past" is probably checked, therefore, MRP can create purchase requisitions in the past when necessary. If this is not desired, you should uncheck this flag.

Regards

Caetano

Former Member
0 Kudos

Hello,

I checked in OPPQ. Start in past is not marked.

Do we have any other settings for this ?

Thanks,
Sankar

former_member183424
Active Contributor
0 Kudos

A quite same discussion was raised in forum

However this discussion was not completed by OP.

Read the reply and check the same accordingly.

former_member197616
Active Contributor
0 Kudos

Hi,

Please check when the MRP was run and when the what is is requirement prior this MRP was run to get created with this PR .

Regards,