Skip to Content
1
Feb 25, 2015 at 03:23 PM

SAP Multi Resource Scheduling

81 Views

Hi All,

We have implemented SAP MRS for our PS system. We started converting old networks into MRS. So we activated the process variant at header level and and set the 'STPL' status for some activities. Its fine till here. When we pulled some networks by Planning Board we could see some other activities that are not related to us. So we have written a small utility program to remove the STPL status for these activities using the FM /MRSS/R3_STATUS_CHANGE.. The STPL status is gone at the activity level in CN22 but the activity still appears in the planning board. I know there will be a demand (GUID) tagged to this activity and we need to remove the status from this GUID. Is there any method to remove this actual demand's status??

Regards,

Praveen..