Auto time stream generation after calendar change

Hi All,

We have a need to automatically generate time streams by report in background.

Normally any change (especially holiday changes or maintenance changes) in calendar is updated first in ECC calendar which is then updated in APO calendar. This change has to be included in the generated time stream which is already created out of those calendars. At present this time stream generation is happening manually when users report any discrepancy finding that they have found in the planning results (which would have old time stream generated not having the calendar change). Sometimes it becomes late for correcting the planning situation. So we would want APO to generate these time streams through regular background job whenever the corresponding calendar has been changed.

Is there any option / alternative available to do this ?

Kindly comment.

Regards,

Durai

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 23, 2015 at 08:18 PM

    Hi Durai,

    Run program: /SAPAPO/TIMESTREAM_UPDATE. It is used to generate the time stream in background.

    Also, please read this document:

    Automation of Factory Calendar Update Between ECC and APO via Process Chain/Batch Jobs

    Kind Regards,

    Mariano