Former Member
Jan 29, 2017 at 06:28 PM

Production order scheduling issue

85 Views Last edit Jan 29, 2017 at 06:44 PM 2 rev

Hi,

I got two issues when i am running business process cycles,

1.When i am converting the planned order in to production order scheduling timings are always less than what i planned.

ex: In routing i given standard values machine time 10 min for 1 PC

when i am creating production order for 20 PC then scheduling time will be 10*20 =200 min or 3.33 hrs but instead of that i am getting 180 min or 3 hrs only.

2.In production order at scheduling i am always getting end time is 24:00 only