Skip to Content
0
Former Member
Feb 13, 2015 at 06:52 PM

Add fields to Algorithm /SAPAPO/HEUR_PLAN_SEQUENCE_MAN

391 Views

Dear Colleagues,


Under certain circumstances Production Scheduler need to sequence some operations manually so we are using Heuristic SAP003 "Schedule Sequence Manually".


In order to achieve this, it would be very useful (and with real added value to the scheduler task) to have some extra field in the "List of operations" when using the algorithm /SAPAPO/HEUR_PLAN_SEQUENCE_MAN

The field we need to add are stored at Planned Order/Production order level and are relevant for all operations in it. The fields are specific characteristics:

The question: Is there a non ABAP way we can ask the system to add the required fields in to the layout of the "Sequence to be planned" list, so the Production Scheduler can take better decisions?

Thanks in advance.

Best regards,

Rubén P.

Message was edited by: Rubén Partido

Attachments

List of fields.png (44.4 kB)