Skip to Content
avatar image
Former Member

Planned orders pushed out of PPDS horizon when run product heurestic manually in RRP3

Hi Experts,

we have been facing an issue , when i run PPDS product heurestics manually in //RRP3 planned orders are getting created out of the PPDS horizon

PPDS Horizon- 120days

Lot size - periodic lot size 1 day

Product Heuristic - Planning of Standard Lots for Conti- I/O

Resource utilization - 100%

Resource availability - 12hrs.

Min lot size - 1000

Rounding  - 1000.

when we increase the Resource avialability or when we run it with Max lot size orders are getting created within PPDS horizon. but we cant change these things.

provided the Attachment

please provide your inputs

Thanks

Raja kiran

ppds issue2.jpg (69.3 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 13, 2015 at 02:34 PM

    Hi Raja,

    What is the heuristic maintained at product level?

    Did you tried with Max.Lot.Size = 1000?

    Thanks, Marius

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Raja,

      Sorry for my late reply!

      Try to play with PPDS horizon. Choose for example180 days and run product heuristic. You should be ok.

      Thanks, Marius  

  • avatar image
    Former Member
    Feb 16, 2015 at 08:12 AM

    Hi Experts,

    Can anyone of you look into this.

    Thanks

    Raja kiran

    Add comment
    10|10000 characters needed characters exceeded