I have a slight problem that I am unable to resolve and hope you may be able to help.

I have Planned and Production Orders loaded onto a resource, when I check the resource: periodic view in the Production Planning Table, I can see the orders are loading as required.

If I go into the Detailed scheduling board and open up the Resource Utilization Chart, it is blank.

I have double checked the PDS's and the Resource Master data (capacity profile) and all looks OK, I have tried different DS profiles with no luck.

Am I missing something.

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Feb 11, 2015 at 03:01 PM

    HI Guy Hall


    check what is staus of planned order

    Regards

    Virender

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello Guy,

      Are you able to see the resource utilization in the report /SAPAPO/CPDS_REPT?

      If yes then you need to set up the configuration for your planning board profile.

      Go to the IMG settings, Maintain planning board profiles, select your planning board profile, select chart 5 (Resource Utilization).

      Then in the Histogram Data select Resource load to the second, and it should help.

      Regards,

      Subhash