Hi Friend ,

We are implementing charm in our landscape . With charm we can track the transports which will be imported after implementing charm.

But client come up with new requirement  that also track the previous transport in charm which were imported before implementing charm .

Guys any idea  is it feasible or not ,  and any suggestion if feasible .

Looking for your great view ideas and suggestions 😊

Thanks

Pramod

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 11, 2015 at 06:11 PM

    You want all transports I assume, for all systems?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Configuration Validation under Root Cause Analysis is what you are after - http://wiki.scn.sap.com/wiki/display/TechOps/ConfVal_Home

      Something to keep in mind though, this will only show the transports after the system was managed.  If they are missing then you will have to go to each system and pull the results manually.  However as ChaRM requires the systems to be in SolMan, you should have extractors working to pull the information into SolMan cubes for reporting purposes.

      By default there is a Dev/Prod backlog report that shows open transports in Dev and transports that haven't made it to Prod yet.

  • avatar image
    Former Member
    Feb 16, 2015 at 09:36 AM

    Hi Pramod

    If earlier transports are released from development system then you need to check this option with cCTS,

    further, you can couple the existing transports if these transports are not released.