I have one Business scenario. Please help me the scenario how to map it.

For a process order qnty: 1000: if the process executes successfully the yield will come in range 990 to 1020 qnty. If the order yield above 1020 will consider as higer yield(suppose yield is 1035; 15 qnty will consider as excess yield for that batch. In this scenario whenever next order is created for the same material, system has to show popup as previous batch is having excess qnty of 15 kg. So order create only for remaining qnty of 985(order standard qnty 1000) only. This is one scenario.

second scenario: While order processing; the qc check will take place; after qc check pass only it will consider as yield. If iqc check failed; again some additives(suppose5 kg) will be added. In this case the order yield will increase.

Here suppose the yield is 1060 kg (because of adding 5kg additives).

For the above two scenarios to get the excess qnty alert when creating next order for the same material is possible to map it through pi sheet in completed order?

that means whenever excess qnty came. the excess qnty should be mention in the pi sheet of the order?

Is This scenario is possible mapping through PI Sheet..? If possible how will map this excess quantity in PI Sheet.

Please guide me.

Thanks,

Sai.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 16, 2017 at 01:25 PM

    Hi, You can try with MQC- material quantity calculation - in your business scenario. please explore.

    Add comment
    10|10000 characters needed characters exceeded

  • May 18, 2017 at 09:32 AM

    Hi Sree,
    Do you only want to solve this scenario using Pi sheets?

    BR,
    Hammad