I need help to implement XI BPM Scenario with Collect Messages Pattern. Here is my Scenario. I am getting four different types of flat files from four interfaces. Using these four files I need to merge using correlation relation and finally have to create One IDoc type to send it to SAP R/3.

But out of these four messages last Message type is an Optional Message. i.e the process has to continue even if forth message is not available by taking first three messages.

Please let me know which pattern is suitable for this scenario.

Thanks.

Siva.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Jan 10, 2006 at 08:46 AM

    Hi,

    I got ur point. let me give a rough idea. may be u can fork and get the three interfaces which are sure to occur and then wait for the fourth interface-optional one for specified time limit. if optional one occurs u could process all the four. if deadline is exceeded just continue with three of interfaces and proceed.Hope this would help.

    Regards,

    Sudharshan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 10, 2006 at 04:19 AM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 10, 2006 at 04:25 AM

    Hi,

    I hope u are receiving four different interfaces.Have a local container variable of simple type integer.you put a fork with four branches after the start step.Each branch has a receive step corresponding to one interface. Then after each of the receive step in each branch put a container operation performing some action on the container variable may be incrementing.so in the end condition of the fork check the value of the container variable i.e you can check if that variable is 3(three of the interfaces have been got).so this ensures that ur fork doesnot wait for all the four.hope this works.

    Regards,

    Sudharshan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Siva

      If you use Fork, then give "Necessary Branches = 4 " in the properties of the Fork step. After this receive the 4 messages and before processing further check for the existence of 4th message(i.e optional one) by using Switch Step.

      I think it will help u.

      -Moorthy

  • avatar image
    Former Member
    Jan 10, 2006 at 06:29 AM

    HI,

    I think you are using an Transformation step(i.e Mapping) inside the BPM. While doing mapping you can check for existence of fourth message and go ahead on this.

    If not you can use switch condition inside the BPM and you can restrict by stating if there is no fourth message do nothing like this,

    Hope this helps..