Moving transports to Quality system, SAP FIORI

Srikanth02
Active Contributor
0 Kudos

Hello Friends,

We are moving our transports to Quality system and is there any manual activities to be done directly in Quality system. Only thing which I remember to do manually in respective systems are below, please correct me if I am wrong

1. Maintain System Aliases

2. Activate and Maintain Services

Or can we do both things in Dev system and move the same to Quality & Production.


Regards,


S.Srikanth

Accepted Solutions (0)

Answers (2)

Answers (2)

vijaybhaskarraju_vegesana
Active Participant
0 Kudos

Hi Srikanth,

It again depends on your QA landscape.

Manual Steps

Back end:

1) All SPRO you need to do it manually in each individual system

2) Manually you can activate and maintain the services in each in /IWFND/MAINT_SERVICE transaction, make sure that your gateway project has been moved.MAke sure your service is routed to correct back end system.

Front End Using WebIDE:

1) The Latest UI5 application name should be updated in your LPD_CUST role and same can be moved through Transport request to QA system.

Make Sure that for all custom Gateway projects,, the custom Gateway service has been added in all environments(DEV, QA ..) in PFCG transaction.

Rest all changes you can move using Transport Request for all Fiori Changes both Backend and Frontend.

Thanks

Vijay

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Srikanth,

You can transport those. Please look at a good document created by Andre Fischer.

Regards,

Masa / SAP Technology RIG