on 02-05-2015 10:50 AM
Hi Experts
there is one internal order in which 1000 profit center is maintained
in Material master -2000 PC is maintained
PO created with F account assignment and in account assignment tab Internal order is maintained.
now the issue is in GR 2000 PC is derived and in IR 1000 profit center is derived
vendor is paid already
now how we can correct this issue, Please guide me.
can we transfer PC 1000 difference to other PC 2000 and how?
Thanks
Hi Kartik,
You have already cleared the vendor balance. So you have to post any one of the below entry.
Bank A/c Dr 1000
Bank A/c Cr 2000
or
Vendor A/c Dr 1000
Venodr A/c Cr 2000
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.