Hi,
When costs are planned in internal & external processing in the network activity, the budget check happens correctly;
However when we plan costs in the tab ' Prim.cost' for a particular cost element in the network activity, it is not subject to budget availability check;Is this a standard behaviour or some config steps are missing ?
We have not maintained any exemption of cost element for availability control; Appreciate any suggestion. Thanks
Hi Sanjoy,
It is a standard behavior. It is just a planned cost, while budget control is only for actual cost and commitments.
Wonder why it "works correctly" for internal NWA, that is also just a planned cost.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Paulo!
By internal activity I meant when we plan for a non-stock item procurement for a internal activity it performs the budget check( perhaps this is because it is creating a commitment).
However, I was trying to compare the functionality of budget control for PM orders vs networks. In PM orders it stops to plan any additional planned hours if the budget exceeds( we have linked the PM order to a WBS having a budget); Likewise I was of the opinion that the same should work for network orders when we have a planned cost exceed the budget; But strangely the control fails in the NWA;