Can SNP generate 2 SNP PPM on same recipe but 2 different BOMs ?

Former Member
0 Kudos

Hello ,

I have two production version with 2 different BOMS, but the recipe is same.

Is it possible to create 2 SNP PPM on this condition at same time

Waiting for your valuable answers

Thanks in advance

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hello,

For the benefits of the others consultants, please indicate the good or the helpful answer!

Thanks, Marius

former_member458819
Active Participant
0 Kudos

Hi

The PVs when CIFed will be created as PPDS PPM.you need to convert PPDS PPM to SNP PPM.

you can created two PPDS PPMs First then you have to generate SNP PPMs from PPDS PPMs

Thanks

Sunil M

Former Member
0 Kudos

Hi Shahin,

Yes, you will have two SNP PPMs on APO side.

The issue after the transfer is which one is the preferred PPM. In this case you can use quota or priority. The version with the highest quota/priority will be chosen as first solution by heuristic and if the capacity is not enough the second version will be used.

Hope that can help you!

Thanks.

Regards, Marius


marianoc
Active Contributor
0 Kudos

Hello,

As you can read in the SAP Help, APO creates one PPM for each Production Version:


The PPM corresponds to the production versionin SAP R/3. The production version is created in the material master or using mass maintenance (transaction C223). The production version links a bill of materialwith a routing (reference operation set, routing, maintenance task list, rate routing) or a master recipe (recipe).

In the APO Core Interface, the BOM and the routing/recipe are consolidated to form a PPM corresponding to the production version and transferred to SAP APO.

Transfer of the Production Process Model (PPM) - Integration via APO Core Interface (CIF) - SAP Libr...

Kind Regards,

Mariano