CTM does not consider orders from ECC process, to calculate the master production plan

Former Member
0 Kudos

Hi gurus, Any of you worked in a scenario where CTM should consider the process firm orders from ECC? I am currently working on a stage of planning, whereby CTM should consider orders from fixed ECC, as projected inventory available for the planning of needs. However at present not the underway. any idea or suggestion? Thank

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hello,

For the benefits of the others consultants, please indicate the good or the helpful answer!

Thanks, Marius

Former Member
0 Kudos

Hello everyone:

The problem is already solved.

I commented that the correct assignment of demand, is done when the needs are sorted by date of availability.

Thank you all for your help

regards

ANDRES BONILLA

thamizhchelvan_gunasekara
Active Participant
0 Kudos

Hi,

It looks like the scenario is due to fix lot size , or minimum lot size.I can see the production planed is always 10. Check your master data.

BR

Thamizh

former_member187488
Active Contributor
0 Kudos

Hello,

Please perform supply simulation for your CTM profile, see whether the fixed order is in the supply list.

Best Regards,
Ada

Former Member
0 Kudos

Hello:

Effectively within the CTM presents simulation, AA order process appears within stcks available.

Thanks por your interest.

Former Member
0 Kudos

Hello Andres,

Please check in the CTM profile, tab Planning Scope, section Supply Selection what is your order selection.

The category of the process order have to be taken in consideration. Also you have to work with planning strategy - Do not delete any Orders.

Hope that can help you.

Thanks.

Regards, Marius 

Former Member
0 Kudos

Hello:

Thanks for the prompt reply. Unfortunately, profile selection orders, are all ATP category.

Here I put an example of behavior that has the result set of CTM

SCENARIO CTM
WEEKSINITIAL123456
DEMAND -100-100-100-100-100-100
PRODUCTION (PLANNED) 10010010010010050
PRODUCTION (FIXED) 50
STOCK 0505050500
SCENARIO EXPECTED
WEEKSINITIAL123456
DEMAND -100-100-100-100-100-100
PRODUCTION (PLANNED) 10050100100100100
PRODUCTION (FIXED) 50
STOCK 000000

thanks for your comments

Former Member
0 Kudos

Hello Andreas,

Please check in the CTM Profile, tab Strategies, Special Strategies if Supply Consumption is enabled. Also the planning mode should be Replan all Orders (tab Planning Strategies).

Thanks.

Regards, Marius