Material with MRP Type 'P2' planning by APO Heuristics

Hi All,

How MRP Type P2 (Firming in PTF, no reschedule) is handled in APO either by SNP or PPDS Heuristics.

As the MRP Type field is not mapped directly to the Product Master in APO, i would like to know how to use the planning heuristic in APO for the materials having MRP Type P2 in ECC when i change the MRP Type to 'X0' and CIF the material to APO for planning equivalent to the MRP Type P2.

Any idea or suggestion from the experts appreciated. Thank you

Regards

PK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 27, 2015 at 08:52 AM

    Hello PK,

    In product master PP/DS tab you will have the PP/DS Plng Time Fence.

    You can use the Heuristc SAP_PP_002 Standard lots heuristic is creating orders within the planning time fence. Which will not delete orders with PP-firmed indicator and specially inside the Planning time fence.

    Please refer SAP consulting noteĀ  441740 - Planning time fence in APO: Documentation foe more details.

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Rupesh,

      Thanks for your reply again. I am not experienced with BadI, I appreciate if you explain the process step-by-step with the TCodes, that would be much easier to understand. Right now i couldn't able to understand how to work with this BadI so i didn't test the scenario in the system.

      Regards

      PK