Structure of the Project is assumed as shown below.

P1

     W0002

               W0003

               W0005

     W0001

               W0006

               W0004    

P1 ( project Definition)

W0001 ..... W0006  ( WBSE elements)

Required format in CJ20N is

P1

     W0001

               W0004

               W0006

     W0002

               W0003

               W0005    

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jan 25, 2015 at 07:50 AM

    Hi ,

    Can you please check the following way:

    Step 1: Select Project WBS ( parent or Level 1 WBS ,if any) -> Select 'Project' from menu bar -> Derive Structure-> Check

    Step 2:

    Select Project WBS ( parent or Level 1 WBS ,if any) -> Select 'Project' from menu bar -> Derive Structure-> Execute.

    Let us now if it works.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

    • Hi

      OK. But in that case I dont see any logic to restructure your project the way you want.

      See,your project hierarchy has many prefixes i.e. G,M,P,L etc. To restructure ,it requires at least the prefix to be unique through out the hierarchy.

      Lets take a very basic example: A pipeline is created by joining node to node and every node is similar to the other in one way or the other. And, if the characteristics of one node differs from  the succeeding node then the link is broken.

      Its the same with your project hierarchy set up.

      Hope you understand what I am trying to say.

      Regards

      Saurabh

  • avatar image
    Former Member
    Jan 24, 2015 at 06:12 AM

    Hi Radhika,

    As far as I know, there is no any automatic functionality in PS to sort the WBS Code. Technically the field value taken as Characters or you can say as a text, So not possible to sort.

    On the other way, you can shift the WBS manually by drag n drop only if you didn't start some work on WBS. Means WBS should be in init status.

    Regards

    Shishir

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 25, 2015 at 09:05 AM

    Hi Radhika,

    Step 2 from Saurabh Tiwari will definitely work for your need.

    Regards

    Terence