on 01-24-2015 4:34 AM
Project structure display in CJ20N based on sorted order of WBSE short id
Structure of the Project is assumed as shown below.
P1
W0002
W0003
W0005
W0001
W0006
W0004
P1 ( project Definition)
W0001 ..... W0006 ( WBSE elements)
Required format in CJ20N is
P1
W0001
W0004
W0006
W0002
W0003
W0005
Hi Radhika,
Step 2 from Saurabh Tiwari will definitely work for your need.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Can you please check the following way:
Step 1: Select Project WBS ( parent or Level 1 WBS ,if any) -> Select 'Project' from menu bar -> Derive Structure-> Check
Step 2:
Select Project WBS ( parent or Level 1 WBS ,if any) -> Select 'Project' from menu bar -> Derive Structure-> Execute.
Let us now if it works.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As mentioned by Maria in his post above, You are using multiple coding mask within a single project and that's the reason system can not adjust the WBS level sequentially.
You may please create a new project and please maintain the one and only that coding mask throughout the project and test this restructuring process there if it works successfully.
Regards
Saurabh
Hi
OK. But in that case I dont see any logic to restructure your project the way you want.
See,your project hierarchy has many prefixes i.e. G,M,P,L etc. To restructure ,it requires at least the prefix to be unique through out the hierarchy.
Lets take a very basic example: A pipeline is created by joining node to node and every node is similar to the other in one way or the other. And, if the characteristics of one node differs from the succeeding node then the link is broken.
Its the same with your project hierarchy set up.
Hope you understand what I am trying to say.
Regards
Saurabh
Hi Radhika,
As far as I know, there is no any automatic functionality in PS to sort the WBS Code. Technically the field value taken as Characters or you can say as a text, So not possible to sort.
On the other way, you can shift the WBS manually by drag n drop only if you didn't start some work on WBS. Means WBS should be in init status.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.