Fixed Requistion Stops MRP Planning Shortfall

Hi,

We are currently using the entry of a fixed P Req to control the ordering of stock from a vendor. The P Req is not assigned a Source of Supply but is used as a flag for a manual consignment process.

The problem is the requirements before the P Req are not being covered additionally by MRP but remain a shortfall until the Fixed P Req is reached. Is this standard behaviour or a setting issue?