Skip to Content
0
Former Member
Jan 06, 2006 at 08:48 AM

Substitution rule: (CJ20N)Move PROJ-PLSEZ to ANIA-AKTIV based on condition

1571 Views

Hi,

I am facing problem in creating a substitution rule in t-code OPSN. On project save in CJ20N PROJ-PLSEZ(finish date) is to be moved to ANIA-AKTIV (activation date).

I am aware of the client specific user exits and i have successfully created a substitution rule for some other fields(Copying standard program RGGBS000 and setting the necessary configuration in SPRO). The problem is that ANIA structure is not available in the program. Could any one please help me out in solving this problem.

Thanks in advance

Rajesh