Non Budgted item

Hi,

We are on ECC6, EHp4, and implementing funds mangement only budgeting part. Now I want to exclude GL where account assignment is WBS or network. For this I made a derivation rule and mentioned the project start numbers and in commitment item, I have selected the commitment item created for non budget item.

My question is, is there any other setting I need to do in configuration, so that system wont ask for budgets for these items?

Please advise

Regards,

Shailesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 14, 2015 at 10:11 AM

    Hi,

    The created dummy commitment item (Non budgeted) and assign to a particular project and maintain the same in FMDERIVE derivation rule.

    Apart from the above settings no need to do any configuration.

    Regards,

    Ravi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 23, 2015 at 10:44 AM

    hi,

    you can also create derivation rule on WBS element when in document WBS number exist then system will not check FM data you can create as such rule.