MRP Area

Dear Team,

My requirement is:

We are using MRP Area for planning. When "MRP Area" is assigned in material master, the "Forecasting View" to be created using the daily background job (night job).

Assume the below example.

Today i have assigned MRP Area in the material master for 20 materials. And for those 20 materials "Forecsting View" to be created automatically with the night batch job.

Tomorrow i am assigning "MRP Area" for another 15 materials. And for those 15 materials "Forecsting View" to be created automatically with the night batch job. I should not consider the yesterday's 20 material also for today.

I am checking the table MDMA. In this table, i do not have field called "Created On". How to fetch the date on which the "MRP Area" view is assigned to materials?

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 17, 2015 at 07:46 AM

    Can anyone please reply?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Try using table MSTA with tcode SE16

      here you can see the changes made in respective views along with creation date

      With best regards,