We are performing an ad-hoc PI process at our client's warehouse. This is completely manual and no RF guns are used. So the requirement is to close all open WTs before starting the PI process and once complete re-create them. Is this possible with SAP EWM?

I know we can cancel all WTs using SCWM/MON transaction, but please let me know what is the best way to re-create WTs. Your response will be greatly appreciated. Thanks in advance.

Sareen.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

At the moment you want to perform ad hoc paper based PI process for a bin, you may consider to manually block the bin using this process. This may help you to recreate tasks.

http://help.sap.com/saphelp_em70/helpdata/en/46/d4ef3ff74b1825e10000000a1553f6/frameset.htm

In case you have more bins to process, I would recommend to cancel WTs and recreate them using LSMW batch input.

Regards

0 Kudos

If you cancel all WTs and then recreate them, it will be not quite correct. So, before you start pi process you should stop all the warehouse processes.

Former Member
0 Kudos

HI Alexander,

THanks for your reply. Could you please help me understand what do you mean by stopping WTS. Also please tell me how to do that. Thanks in advance.