Can you define Leadtime offsets in RCCP?
I make a product that takes 3 months
It goes across 3 Bottlenect resources
Production is schedule for 3000 due march 31.
In MC88 the Production Line is in Monthly Resolution
So the 3000 production in March creates Capacity Requirements in March for all 3 Bottlenecks
In Reality, not all 3 Bottlenecks will support the 3000 march 31 Production in MARCH
Some of the 3000 March 31 Production will create load on the Bottleneck resources in jan and Feb
So this is the business sceanario. I hope it is clear. For the 3000 due in March....that take 3 months to make, how do I show capacity requirements in alignment with where they will really happen?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paul
Did you try to use a routing instead of the Rough-Cut Planning Profile?
You can do that using selection ID 01 instead of 03 on customizing. See the wiki below for details:
http://wiki.scn.sap.com/wiki/display/ERPMan/Rough-Cut+Capacity+Planning+on+SOP
BR
Caetano
Hi Paul,
for these things to check, we need to have information on the masterdata set up:
workcenter:
Routing:
what are the results shown by MRP run? and you might want to look into capacity evaluation and leveling transaction also.
Regards,
Sandeep
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.