Can you define Leadtime offsets in RCCP?

Can you define Leadtime offsets in RCCP?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jan 13, 2015 at 07:42 PM

    Hi Paul

    Can you please provide more details about your issue? Please describe your business requirement and the scenario where you need this functionality.

    Please read the blog Asking Good Questions in the SCN Discussion Spaces will help you get Good Answers, which may be useful to you.

    Best regards

    Caetano Almeida

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 16, 2015 at 04:40 PM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 16, 2015 at 04:46 PM

    I make a product that takes 3 months

    It goes across 3 Bottlenect resources

    Production is schedule for 3000 due march 31.

    In MC88 the Production Line is in Monthly Resolution

    So the 3000 production in March creates Capacity Requirements in March for all 3 Bottlenecks

    In Reality, not all 3 Bottlenecks will support the 3000 march 31 Production in MARCH

    Some of the 3000 March 31 Production will create load on the Bottleneck resources in jan and Feb

    So this is the business sceanario. I hope it is clear. For the 3000 due in March....that take 3 months to make, how do I show capacity requirements in alignment with where they will really happen?

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Paul,

      for these things to check, we need to have information on the masterdata set up:

      workcenter:

      •   standard value keys and formulae (for capacity and scheduling).
      • finite capacity scheduling has been chosen or not?
      • available capacity and utilization details.

      Routing:

      • what are the quantities and times defined for the operations.
      • whether lead time scheduling has been chosen during MRP run?

      what are the results shown by MRP run? and you might want to look into capacity evaluation and leveling transaction also.

      Regards,

      Sandeep