SAP PI Transport process using CTS+ - DEV-> Qualilty-> Production

Hi Folks,

I have three environments in SAP PI- development, quality and production environment. We have separate SLD's for all three. We follow a CTS+ methodology for transports.

The method we currently follow is that when we transport from Development to quality, we provide a Transport number to basis team(development TR number) and then when we transport from quality to production we gain create a new Transport number in quality and then send the same to Production and not the development one.

We do have transport routes and transport targets created for both like

Dev->Prod

Dev->QA->Prod

I have been asked to give a justification that why we follow Dev->QA->Prod i.e. different TR concept rather than Dev->Prod i.e one single TR.

Kindly tell me the best practice and supporting document if any which I can provide as my justification..

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 13, 2015 at 03:19 PM

    Monika,

    Change Management Service (CMS), recommends transporting same TR from DEV -> to QA -> to PRD. One of the strengths of SAP, is it's transport system (same TR till PRD).

    There is no advantage in raising new TR in QA (it's unnecessary overhead, you may miss to transport some changes).

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Monika,

      apart from any document you can explain it that avoid multiple TR helps to keep a track on the version available in eac environment. In general QA is supposed to be a copy of Prod. and so nothing directly from DEV should be moved to Prod.

      Regards